These are some samples of past contracts:
M/Y "DUBAWI"
Rebuilding of all the exterior Teak Decking areas and steps
Burmese Teak of Super Decking Quality was used, 1,176 m2 have been replaced.5.
Commencement of works on October 2008-09-29 and completion of works on July 2009-07-28.5.
The project took place at Dubai U.A.E5.
Client’s name: Platinum Yachts FZCO / www.platinumyachts.ae5.
Click here for more pics
M/S "DUBAI MAGIC"
Rebuilding of all the exterior Teak Decking areas and steps
Burmese Teak of Super Decking Quality was used, 356 m2 have been replaced.
Commencement of works on May 2007-05-18 and completion of works on September 2007-09-30.
The project took place at Dubai U.A.E
Client’s name: Platinum Yachts FZCO / www.platinumyachts.ae
Click here for more pics
M/Y "RAGAZZA"
Rebuilding of all the exterior Teak Decking areas and steps
Burmese Teak of Super Decking and Decking Quality was used, 370 m2 have been replaced.
Commencement of works on March 2005-03-5 and completion of works on June 2005-06-12.
The project took place at Greece – Perama Hellenic Shipyards.
Click here for more pics
M/Y "MELISE"
General Sanding of the Exterior Teak Decking Areas, Teak Solid Construction and fitting of the external Teak dining table
Commencement of works on April 2009-04-5 and completion of works on May 2009-05-12.
The project took place at Greece – Alimos Marina.
Click here for more pics
M/Y "Wishpers" ( Cantieri Dipisa 42m) Built in 1985
Rebuilding of main and sun decks. Total area of over 200 square meters.
Teak Burma of Super-Decking Quality was used
Commencement of work in June 2003 and completion within 30 working days.10 to 12 hours of work per day and at least 8 hours on Saturdays. 8 artisans were used for this project.
Click here for more pics
M/Y "Orion" Built in 2002
Building of Main, Upper and Sun decks. Total area of over 170 square meters
Caping rails over 160 running meters
Teak Burma of Super-Decking quality was used
Commencement of work in March 2003 and completion within 30 working days. 10 to 12 hours of work per day and at least 8 hours on Saturdays. 8 artisans were used for this project.
Click here for more pics
M/Y "Omega" Built in 2003
Building of Main, Upper, Bridge, Sun Decks . Total area over 750 square meters.
Teak Burma of Super-Decking quality was used
Commencement of work in February 2004 and completion withing 90 working days. 10 to 12 hours of work per day and at least 8 hours on Saturdays. 14 artisans were used for this project.
Click here for more pics
M/Y "BLUE HUNTER" 20m. FERRETI
Construction of Teak Deck on the swiming platform.
Materials: Burma Teak-Super Decking, Mahogan Marine plywood, Simson Bostik HOLLAND Deck Caulk and Rubber Glue.
Commencement of work in 09 NOVEMBER 2006 and completion within 14 working days. 10 hours work per day and at least 7 hours on Saturdays. 2 artisans were used for this project.
Click here for more pics
M/Y "Blue Symphonie" 26m
RECAULKING OF MAIN AND SUN DECK
TOTAL RUNNING METERS: 2.100
Commencement of work in 20 NOVEMBER 2005 and completion within 25 working days.
10 hours work per day and at least 7 hours on Saturdays. 5 artisans were used for this project.
Click here for more pics
M/Y 42m. (Work in progress)
Rebuilding of all Teak Decking areas and rebuilding of all exterior capping-rails.
Materials: Burma Teak-Decking & F.E.Q selected mixed qualities, marine grade okoume plywood, Simson Bostik HOLLAND marine adhesives.
Commencement of work in 18 of May 2007 and completition of work in 4,5 months 30 of Semptember 2007. 7 artisans were used for this project.
356 m2 were rebuilded.
Click here for more pics
For any further information or references please do not hesitate to contact us.
|
|